Interior Drywall Specifications
Interior Job Condition Specifications For The Application Of
Drywall Joint Compounds, Drywall Textures, And Paints/Coatings
1. Scope
All walls, partitions, and ceilings to which drywall joint compounds, drywall textures (where applicable), and paints/coatings are to be applied are included.
- 1.1 This specification covers the conditioning of gypsum board and concrete prior to the application of drywall joint compounds, drywall textures, and paints/coatings.
- 1.2 This specification covers the interior job conditions during the application of drywall joint compounds, drywall textures, and paints/coatings.
- 1.3 All materials to be used in accordance with all codes, specifications, and manufacturer’s recommendations.
2. Substrate Preparation
- 2.1 The gypsum board shall be maintained at a minimum temperature of 10°C (50°F), and be dry for at least 48 hours prior to the application of drywall joint compounds, drywall textures, and paints/coatings.
- 2.2 Concrete surfaces shall be aged at least 60 days prior to the application of drywall joint compounds, drywall textures, and paints/coatings. All efflorescence, form release agents, dust, or other surface contaminates shall be removed. The concrete surface shall be dry. Exposed metal shall be hand-tool cleaned and primed with a rust-inhibitive primer. The concrete surface shall be maintained at a minimum temperature of 10°C (50°F).
3. Interior Job Conditions
- 3.1 A minimum temperature of 10°C (50°F) shall be maintained continuously for the application of the drywall joint compounds, drywall textures, and paints/coatings until dry.
- 3.2 Continuous ventilation shall be provided to allow proper drying.
- 3.3 Whenever possible, permanent heating and ventilation systems should be utilized.
- 3.4 Whenever possible, permanent lighting should be utilized.
- 3.4.1 Job site lighting may not be representative of final lighting. Inspection shall take place under job site lighting conditions.
- 3.5 All drywall joint compounds shall be dry or, with setting type drywall joint compounds, hardened (set) prior to the application of subsequent coats.
- 3.6 All drywall joint compounds shall be dry prior to the application of drywall textures and paints/coatings.
4. Drywall Joint Compound, Drywall Texture, and Paint/Coating Application
- 4.1 Drywall joint compounds, drywall textures, and paints/coatings are to be mixed and applied in accordance with the manufacturer’s recommendations.
5. Interior Conditions for Finished Buildings
- 2.1 All finished walls, partitions, and ceilings shall be maintained at a minimum temperature of 10°C (50°F).
3/20/96
Members
- Benjamin Moore & Co •
- BPB Gypsum •
- BPB Marco •
- Westrock, Inc •
- Freeman Products •
- Georgia Pacific Corporation •
- Hamilton Materials, Inc. •
- LaFarge North America •
- Magnum Products •
- National Gypsum Company •
- Rapid Set Cement •
- Saint-Gobain Technical Fabrics America, Inc •
- Sherwin-Williams Company •
- Solid Products, Inc. •
- Southern Wall Products •
- Supro Corporation •
- Tool World, Inc •
- United States Gypsum Company
Associates
- Akzo Nobel Surface Chemistry, Inc. •
- Ames taping Tools Company •
- Bayer Chemicals •
- Canadian Gypsum Company Corp. •
- Clinch-On Cornerbead •
- Dow Chemical Company •
- Floridin Company Div. of ITC Industrial •
- Forbo Adhesives •
- Hercules Chemica • l
- IMV Nevada •
- J.M. Huber, Incorporated •
- Nobel Materials, Inc. •
- Tate & Lyle •
- Troy Chemical •
- Zemex Industrial Minerals
Honorary Members
- Association of Wall and Ceiling Industries (AWCI • )
- Drywall Information Trust Fund (DITF) •
- Northwest Wall and Ceiling Bureau •
- Painting and Decorating Contractors of America (PDCA) •
- Technical Services Information Bureau •
- The Gypsum Association